Scope

Extension + Refit

Area Added

+600 sq ft

Duration

16 weeks

Budget Band

£180k–£250k

Overview

A structural rear extension and a full refit for a new high-street tenant. Works included new shopfront, services relocation, accessible WC, and upgraded HVAC. Delivery coordinated with landlord approvals and utilities.

  • Steelwork, foundations, and shell extension
  • New MEP distribution and HVAC upgrades
  • Retail-grade lighting, flooring, and POS counters
  • Shopfront replacement and signage coordination

Timeline

  1. Weeks 1–3: Strip-out, temporary works
  2. Weeks 4–7: Steel, extension shell & roof
  3. Weeks 8–11: First/second fix MEP
  4. Weeks 12–14: Finishes and fixtures
  5. Weeks 15–16: Testing and handover